Por favor, use este identificador para citar o enlazar este ítem: https://hdl.handle.net/10495/36132
Registro completo de metadatos
Campo DC Valor Lengua/Idioma
dc.contributor.advisorMendoza Herrera, Rafael Ricardo-
dc.contributor.authorVargas Bermúdez, María Juliana-
dc.date.accessioned2023-08-02T16:23:07Z-
dc.date.available2023-08-02T16:23:07Z-
dc.date.issued2023-
dc.identifier.urihttps://hdl.handle.net/10495/36132-
dc.description.abstractRESUMEN : En este documento se evidencia el proyecto realizado con el fin de mejorar la disponibilidad de pasta en el proceso de prensado en la planta de fabricación de baldosas de pared, ubicada en Girardota, perteneciente a la división de negocio Superficies, Materiales y Pinturas de la Organización Corona. El proceso de prensado viene experimentando paradas mayores y menores debido a la falta de pasta, la cuál es el insumo principal del proceso de producción de baldosas, que puede ser causada por diferentes factores como atascos en el sistema de transporte o fallos en los componentes tales como: recorrido ininterrumpido del tripper, fallas mecánica en bandas o tolvas. Para encontrar causas adicionales y cumplir con el objetivo principal de este proyecto que es disminuir el tiempo de inactividad en las prensas causado por falta de pasta, la metodología que se utilizó es de carácter mixto y se llevará a cabo a través de un ciclo de mejora, basado en la metodología Lean Six Sigma “DMAIC”, fases a saber: definición, medición análisis, implementación, control y cierre. A partir de los resultados de la implementación de la metodología descrita, se propone a la Organización realizar las siguientes mejoras: baliza y alarma sonora en el tripper; marcador de falta de pasta en el tablero de bandas silos como indicador de paros; incluir mecanismo rompe grumos en el divertí y en el sensor de nivel de pasta de las tolvas; aumento de frecuencias de vibraciones del tamiz. Estas propuestas quedan sujetas a la aprobación y autorización de presupuesto necesario para su implementación.spa
dc.description.abstractABSTRACT : This document shows the project carried out in order to improve the availability of paste in the pressing process at the wall tile manufacturing plant, located in Girardota, belonging to the Surfaces, Materials and Paints business division of the Corona Organization. The pressing process has been experiencing major and minor stoppages due to the lack of paste, which is the main input of the tile production process, which can be caused by different factors such as jams in the transport system or failures in the components such as: uninterrupted tripper travel, mechanical failures in belts or presses. In order to find additional causes and fulfill the main objective of this project, which is to reduce the downtime in the presses caused by lack of paste, the methodology that will be used is mixed and will be carried out through an improvement cycle, based on the Industrial Engineering methodology "DMAIC", with six phases: definition, measurement, analysis, implementation, control and closure. After the application of this methodology, the following improvements are proposed to the Organization: beacon and sound alarm in the tripper; lack of pulp marker on the silo belt board as a stop indicator; inclusion of a lump breaker mechanism in the diverter and in the pulp level sensor in the hoppers; increase of vibration frequencies of the sieve. These proposals are subject to approval and authorization of the budget necessary for their implementation.spa
dc.format.extent38spa
dc.format.mimetypeapplication/pdfspa
dc.language.isospaspa
dc.type.hasversioninfo:eu-repo/semantics/draftspa
dc.rightsinfo:eu-repo/semantics/openAccessspa
dc.rights.urihttp://creativecommons.org/licenses/by-nc-nd/2.5/co/*
dc.titleReducción de tiempos perdidos en prensas ocasionados por falta de pasta a través de un ciclo de mejoramiento, en el proceso de producción de Baldosas en la Organización Corona Sede Girardotaspa
dc.typeinfo:eu-repo/semantics/bachelorThesisspa
oaire.versionhttp://purl.org/coar/version/c_b1a7d7d4d402bccespa
dc.rights.accessrightshttp://purl.org/coar/access_right/c_abf2spa
thesis.degree.nameIngeniera Industrialspa
thesis.degree.levelPregradospa
thesis.degree.disciplineFacultad de Ingeniería. Ingeniería Industrialspa
thesis.degree.grantorUniversidad de Antioquiaspa
dc.rights.creativecommonshttps://creativecommons.org/licenses/by-nc-sa/4.0/spa
dc.publisher.placeMedellín, Colombiaspa
dc.type.coarhttp://purl.org/coar/resource_type/c_7a1fspa
dc.type.redcolhttps://purl.org/redcol/resource_type/TPspa
dc.type.localTesis/Trabajo de grado - Monografía - Pregradospa
dc.subject.lembMejoramiento de procesos-
dc.subject.lembControl del proceso-
dc.subject.lembOptimización-
dc.subject.lembDesarrollo de procesos-
dc.subject.proposalCiclo de mejoraspa
dc.subject.proposalDisponibilidadspa
dc.subject.proposalAnálisis causa raízspa
dc.subject.proposalLean Six Sigmaspa
Aparece en las colecciones: Ingeniería Industrial

Ficheros en este ítem:
Fichero Descripción Tamaño Formato  
VargasMaria_2023_CicloMejoraTiempos.pdfTrabajo de grado de pregrado1.02 MBAdobe PDFVisualizar/Abrir


Este ítem está sujeto a una licencia Creative Commons Licencia Creative Commons Creative Commons